Renovation of Hermesbrug
The Hermesbrug bridge will be renovated in 2027. Inspections have shown that this bridge from 1961 has reached the end of its technical service life. The bridge can safely be used, but large-scale renovation is necessary to ensure it remains a reliable connection in future. With this investment, we will continue to guarantee Leeuwarden’s accessibility and prevent malfunctions and unexpected bridge failure.
Activities
The works will take place from 15 February to 23 July 2027. During this period, Hermesbrug will be closed to all road traffic. The works cannot be postponed any longer, because the inspection shows that the bridge has reached the end of its service life.
Work on the bridge will take place on working days from 7 am to 7 pm. In principle, no work will be carried out in the evenings, at night and at the weekends. This can only be deviated from when the waterway is blocked (see further down on this page), for example when hoisting, removing or mounting bridge components.
What are we going to do
The bridge’s superstructure will be replaced. We will also carry out maintenance on different parts around the bridge. The Hermesbrug bridge will furthermore be connected to the central bridge control system in Swettehûs. This will allow the bridge to be controlled remotely and make better monitoring possible. As a result, the bridge will be less prone to errors and more easy to manage.
The work will be carried out by Solidd Steel Structures from Sumar.
Access
The Hermesbrug bridge plays an important role in Leeuwarden’s traffic network. It is the only north-south connection between Verlaatsbrug and Slauerhoffbrug on this section of the ring road. As a result, many road users will be affected by the work to be carried out.
To keep the city accessible, traffic will be diverted:
- Car traffic will use Slauerhoffbrug.
- Cyclists will be redirected to Verlaatsbrug.
- Temporary diversion signs will be placed along important routes. Motorists must account for a different route and possibly a longer travel time. The local authority will take care of clear signage for cyclists.
Accessibility of companies
Companies will remain accessible while the work is carried out. The local authority will work out the traffic measures in greater detail and enter into conversation with entrepreneurs to identify any bottlenecks at an early stage. In doing so, we will consider accessibility, deliveries and business operations.
Accessibility of the waterway
The waterway will remain largely available. It will only be temporarily closed during 5 short periods. In total, this concerns 15 days:
- 20 and 21 February 2027;
- 6 and 7 March 2027;
- 21 to 23 April 2027;
- 1 and 2 May 2027;
- 24 to 28 June 2027.
These closures will be announced in advance so the shipping industry can take this into account.
Broader bridge approach
Just like many other municipalities, Leeuwarden is faced with a considerable replacement and maintenance task with regard to bridges and other infrastructure. That is why the local authority is working on a systematic approach in which bridges are inspected and renovated or replaced where necessary. Effective maintenance and timely replacement will prevent failures, higher costs and unexpected closures.
Frequently asked questions
- Is the Hermesbrug bridge unsafe?
- No. The bridge can safely be used. The replacement is not because of an acute safety issue. The inspection has shown, however, that the bridge has reached the end of its technical service life. By investing now, we will prevent bigger problems and additional maintenance down the road.
- Why is the bridge being replaced rather than repaired?
- For bridges, the local authority always looks at the most effective solution. Where possible, we will opt for renovation and service life extensions. A technical inspection has shown that, for Hermesbrug, replacement of the superstructure is necessary to make the bridge reliable again for the coming decades.
- What will be the results of this renovation?
- Once the renovation work is complete, Leeuwarden will again have a safe, reliable and future-proof bridge expected to last several more decades. The connection to the central bridge control system will moreover allow for more efficient management and make it less liable to break down.
Do you have any questions?
Contact the City of Leeuwarden.
Quick to:
Activities
The works will take place from 15 February to 23 July 2027. During this period, Hermesbrug will be closed to all road traffic. The works cannot be postponed any longer, because the inspection shows that the bridge has reached the end of its service life.
Work on the bridge will take place on working days from 7 am to 7 pm. In principle, no work will be carried out in the evenings, at night and at the weekends. This can only be deviated from when the waterway is blocked (see further down on this page), for example when hoisting, removing or mounting bridge components.
What are we going to do
The bridge’s superstructure will be replaced. We will also carry out maintenance on different parts around the bridge. The Hermesbrug bridge will furthermore be connected to the central bridge control system in Swettehûs. This will allow the bridge to be controlled remotely and make better monitoring possible. As a result, the bridge will be less prone to errors and more easy to manage.
The work will be carried out by Solidd Steel Structures from Sumar.
Access
The Hermesbrug bridge plays an important role in Leeuwarden’s traffic network. It is the only north-south connection between Verlaatsbrug and Slauerhoffbrug on this section of the ring road. As a result, many road users will be affected by the work to be carried out.
To keep the city accessible, traffic will be diverted:
- Car traffic will use Slauerhoffbrug.
- Cyclists will be redirected to Verlaatsbrug.
- Temporary diversion signs will be placed along important routes. Motorists must account for a different route and possibly a longer travel time. The local authority will take care of clear signage for cyclists.
Accessibility of companies
Companies will remain accessible while the work is carried out. The local authority will work out the traffic measures in greater detail and enter into conversation with entrepreneurs to identify any bottlenecks at an early stage. In doing so, we will consider accessibility, deliveries and business operations.
Accessibility of the waterway
The waterway will remain largely available. It will only be temporarily closed during 5 short periods. In total, this concerns 15 days:
- 20 and 21 February 2027;
- 6 and 7 March 2027;
- 21 to 23 April 2027;
- 1 and 2 May 2027;
- 24 to 28 June 2027.
These closures will be announced in advance so the shipping industry can take this into account.
Broader bridge approach
Just like many other municipalities, Leeuwarden is faced with a considerable replacement and maintenance task with regard to bridges and other infrastructure. That is why the local authority is working on a systematic approach in which bridges are inspected and renovated or replaced where necessary. Effective maintenance and timely replacement will prevent failures, higher costs and unexpected closures.
Frequently asked questions
- Is the Hermesbrug bridge unsafe?
- No. The bridge can safely be used. The replacement is not because of an acute safety issue. The inspection has shown, however, that the bridge has reached the end of its technical service life. By investing now, we will prevent bigger problems and additional maintenance down the road.
- Why is the bridge being replaced rather than repaired?
- For bridges, the local authority always looks at the most effective solution. Where possible, we will opt for renovation and service life extensions. A technical inspection has shown that, for Hermesbrug, replacement of the superstructure is necessary to make the bridge reliable again for the coming decades.
- What will be the results of this renovation?
- Once the renovation work is complete, Leeuwarden will again have a safe, reliable and future-proof bridge expected to last several more decades. The connection to the central bridge control system will moreover allow for more efficient management and make it less liable to break down.