Redesign of Huizumerlaan
We are redesigning the Huizumerlaan. It will become a bicycle boulevard: a comfortable route for cyclists, where cars are guests. We will also install a new sewer for rainwater. The construction work will last until late December 2025 and will be carried out in five phases. During each phase, part of Huizumerlaan will be completely closed to traffic.
Work schedule
Phase 1: Schrans – Oostergoweg
- 18 August to mid-October 2025.
We will renovate the street and install additional drainage points for rainwater. The bicycle crossing at Oostergoweg will be closed from 18 August.
Phase 2: Oostergoweg – Sportlaan
- Early September to 26 October 2025.
A sewer for rainwater will be installed alongside the existing sewer. The roadway will be broken open and redesigned.
Phase 3: Sportlaan – Jansoniusstraat
- From mid-September to 26 October 2025.
We will continue work on the sewer. The street and footpaths will also be renovated.
Phase 4: Huizumerlaan/Jansoniusstraat crossroads
- From 17 October to 26 October 2025.
Construction work on the crossroads. This part will be completely closed off.
Phase 5: Jansoniusstraat – Pelsweg
- From 27 October to late December 2025.
This is the final phase. In late December, we will add the final layer of asphalt to the entire street.
Diversions
Diversions will be signposted.
Stay informed
The schedule may change depending on the weather or other circumstances. Up-to-date information will be available in the BouwApp. Look up Huizumerlaan for updates, diversions and contact details.
Contact
Do you have any questions about the construction work? Contact environmental manager Nico Visser of Koninklijke Sjouke Dijkstra via huizumerlaan@sjoukedijkstra.nl or 06 2205 1541.
Do you have any questions about the project? Contact the City of Leeuwarden.
Work schedule
Phase 1: Schrans – Oostergoweg
- 18 August to mid-October 2025.
We will renovate the street and install additional drainage points for rainwater. The bicycle crossing at Oostergoweg will be closed from 18 August.
Phase 2: Oostergoweg – Sportlaan
- Early September to 26 October 2025.
A sewer for rainwater will be installed alongside the existing sewer. The roadway will be broken open and redesigned.
Phase 3: Sportlaan – Jansoniusstraat
- From mid-September to 26 October 2025.
We will continue work on the sewer. The street and footpaths will also be renovated.
Phase 4: Huizumerlaan/Jansoniusstraat crossroads
- From 17 October to 26 October 2025.
Construction work on the crossroads. This part will be completely closed off.
Phase 5: Jansoniusstraat – Pelsweg
- From 27 October to late December 2025.
This is the final phase. In late December, we will add the final layer of asphalt to the entire street.
Diversions
Diversions will be signposted.
Stay informed
The schedule may change depending on the weather or other circumstances. Up-to-date information will be available in the BouwApp. Look up Huizumerlaan for updates, diversions and contact details.
Contact
Do you have any questions about the construction work? Contact environmental manager Nico Visser of Koninklijke Sjouke Dijkstra via huizumerlaan@sjoukedijkstra.nl or 06 2205 1541.
Do you have any questions about the project? Contact the City of Leeuwarden.