Redesign of Huizumerlaan
The work on Huizumerlaan has been temporarily suspended. Old electricity cables are located beneath the street here. These are not safe and have caused a power outage. It was therefore decided to temporarily suspend the work. Grid manager Liander will replace the cables first. We expect to be able to resume redevelopment of the street in early January 2026.
Work schedule
We will continue redeveloping Huizumerlaan once grid manager Liander is done. It will become a bicycle boulevard: a pleasant route for cyclists, where cars are guests. We will also install a new sewer for rainwater. The work will be carried out in five phases. During each phase, part of Huizumerlaan will be completely closed to traffic.
Phase 1: Schrans – Oostergoweg
- We will renovate the street and install additional drainage points for rainwater. The bicycle crossing at Oostergoweg will be closed from 18 August.
Phase 2: Oostergoweg – Sportlaan
- A sewer for rainwater will be installed alongside the existing sewer. The roadway will be broken open and redesigned.
Phase 3: Sportlaan – Jansoniusstraat
- We will continue work on the sewer. The street and footpaths will also be renovated.
Phase 4: Huizumerlaan/Jansoniusstraat crossroads
- Construction work on the crossroads. This part will be completely closed off.
Phase 5: Jansoniusstraat – Pelsweg
- This is the final phase. In late December, we will add the final layer of asphalt to the entire street.
Diversions
Diversions will be signposted.
Stay informed
The schedule may change depending on the weather or other circumstances. Up-to-date information will be available in the BouwApp. Look up Huizumerlaan for updates, diversions and contact details.
Contact
Do you have any questions about the construction work? Contact environmental manager Nico Visser of Koninklijke Sjouke Dijkstra via huizumerlaan@sjoukedijkstra.nl or 06 2205 1541.
Do you have any questions about the project? Contact the City of Leeuwarden.
Work schedule
We will continue redeveloping Huizumerlaan once grid manager Liander is done. It will become a bicycle boulevard: a pleasant route for cyclists, where cars are guests. We will also install a new sewer for rainwater. The work will be carried out in five phases. During each phase, part of Huizumerlaan will be completely closed to traffic.
Phase 1: Schrans – Oostergoweg
- We will renovate the street and install additional drainage points for rainwater. The bicycle crossing at Oostergoweg will be closed from 18 August.
Phase 2: Oostergoweg – Sportlaan
- A sewer for rainwater will be installed alongside the existing sewer. The roadway will be broken open and redesigned.
Phase 3: Sportlaan – Jansoniusstraat
- We will continue work on the sewer. The street and footpaths will also be renovated.
Phase 4: Huizumerlaan/Jansoniusstraat crossroads
- Construction work on the crossroads. This part will be completely closed off.
Phase 5: Jansoniusstraat – Pelsweg
- This is the final phase. In late December, we will add the final layer of asphalt to the entire street.
Diversions
Diversions will be signposted.
Stay informed
The schedule may change depending on the weather or other circumstances. Up-to-date information will be available in the BouwApp. Look up Huizumerlaan for updates, diversions and contact details.