Work schedule

Phase 1: Schrans – Oostergoweg

  • 18 August to mid-October 2025.
    We will renovate the street and install additional drainage points for rainwater. The bicycle crossing at Oostergoweg will be closed from 18 August.

Phase 2: Oostergoweg – Sportlaan

  • Early September to 26 October 2025.
    A sewer for rainwater will be installed alongside the existing sewer. The roadway will be broken open and redesigned.

Phase 3: Sportlaan – Jansoniusstraat

  • From mid-September to 26 October 2025.
    We will continue work on the sewer. The street and footpaths will also be renovated.

Phase 4: Huizumerlaan/Jansoniusstraat crossroads

  • From 17 October to 26 October 2025.
    Construction work on the crossroads. This part will be completely closed off.

Phase 5: Jansoniusstraat – Pelsweg

  • From 27 October to late December 2025.
    This is the final phase. In late December, we will add the final layer of asphalt to the entire street.

Diversions

Diversions will be signposted.

Stay informed

The schedule may change depending on the weather or other circumstances. Up-to-date information will be available in the BouwApp. Look up Huizumerlaan for updates, diversions and contact details.